ABC Project Evaluation using CPM/PERT and Crash Program Methods in PT PAC Engineering
Dion Jonadi1, Hendri Kus Julius2, Suwendy3, Yuli Eni4

1Dion Jonadi, Management Department, BINUS Business School Undergraduate Program, Bina Nusantara University, Jakarta, Indonesia.
2Hendri Kus Julius, Management Department, BINUS Business School Undergraduate Program, Bina Nusantara University, Jakarta, Indonesia.
3Suwendy, ManagementDepartment, BINUS Business School Undergraduate Program, Bina Nusantara University, Jakarta, Indonesia.
4Yuli Eni*, Management Department, BINUS Business School Undergraduate Program, Bina Nusantara University, Jakarta, Indonesia.
Manuscript received on July 02, 2020. | Revised Manuscript received on July 10, 2020. | Manuscript published on August 30, 2020. | PP: 99-103 | Volume-9 Issue-6, August 2020. | Retrieval Number: B2881129219/2020©BEIESP | DOI: 10.35940/ijeat.B2881.089620
Open Access | Ethics and Policies | Cite | Mendeley
© The Authors. Blue Eyes Intelligence Engineering and Sciences Publication (BEIESP). This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/)

Abstract: This study was made aiming to determine the optimal time needed in the implementation of the ABC project by using the CPM / PERT method, to determine the time needed in the implementation of the ABC project using the Crashing Project method and to find out the additional costs required in using the Crashing Project method. The analytical research method used is the CPM / PERT method and the Crashing Project. The results of this study show that the ABC project has a critical path that must be done, namely the A-B-C-D-E-H-I-J-K-M-N-O-R-S-T-U activity within 99 days. The cost calculated through Crashing Project is Rp. 219,300,000 and can save time to 83 days of project execution. Consumer demand to complete the project within 90 days. There fore the results of the Crashing Project get the amount of the cost of Rp. 6,200,000. The conclusion is the ABC project can be completed within 90 days using the CPM / PERT method and the Crashing Project (DJ, HKJ and S)
Keywords: CPM/PERT, Crashing Project