Selection of Alternative Working Methods using the Crashing and Microsoft Project Methods
Muhammad Djuneydi1, Yudi Setio Prabowo2, M. Oka Mahendra3

1Muhammad Djuneydi, Department of Civil Engineering, University of Serang Raya, Kota Serang, Banten, Indonesia.
2Yudi Setio Prabowo, Department of Civil Engineering, University of Serang Raya, Kota Serang, Banten, Indonesia.
3M. Oka Mahendra, Department of Civil Engineering, University of Serang Raya, Kota Serang, Banten, Indonesia.
Manuscript received on 15 April 2023 | Revised Manuscript received on 04 June 2023 | Manuscript Accepted on 15 June 2023 | Manuscript published on 30 June 2023 | PP: 127-139 | Volume-12 Issue-5, June 2023 | Retrieval Number: 100.1/ijeat.E41300612523 | DOI: 10.35940/ijeat.E4130.0612523

Open Access | Editorial and Publishing Policies | Cite | Zenodo | Indexing and Abstracting
© The Authors. Blue Eyes Intelligence Engineering and Sciences Publication (BEIESP). This is an open access article under the CC-BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/)

Abstract: In carrying out the PPLP Banten Building construction project, it experienced delays. The causes of delays are the addition of time, changes in shop drawings and material delays. Then the solution in theMicrosoft project is an alternative crashing method of 4 hours of overtime and work shifts. The research results obtained 18 jobs that are on the critical path of 43 jobs. The normal total duration is 942 days and the normal fee is Rp. 569.100.000 using AHSP. The results obtained are the total duration of the alternative crashing 4 hours of overtime work is 678 days, while the work shift is 530 days, the AHSP Project produces an alternative total cost of 4 hours overtime of Rp. 3.066.675.000 and work shifts with accident costs of Rp. 1.223.565.000. The alternative cost of 4 hours of overtime using the AHSP project is Rp. 193.067.245,23 and work shifts using the AHSP project of Rp. 33.638.199,58 then the work shift alternative is more economical and was chosen to be applied to the project. The results of the comparison of direct and indirect costs for the 4-hour overtime alternative are direct costs Rp. 9.672.161.032,2 indirect costs Rp. 1.322.728.805,77 and direct costs for work shift alternatives Rp.9.512.731.986,58 costs Rp. 1.273.456.116,78 then the work shift alternative is more economical and is chosen to be applied to the project.
Keywords: Microsoft Project, Crashing, Overtime, Shifts, Time, Costs.